Answer:
$23,122
Explanation:
Calculation to determine the overhead cost assigned to Product C9 under activity-based costing
First step is to calculate the cost allocation to machining activity and order filling
MACHINING
Equipment depreciation (0.60 : 0.10 : 0.30)
Machining=$47,000 x 0.60 = $28,200
Supervisory expense (0.60 : 0.20 : 0.20) Machining=$6,000 x 0.60 = $3600
Total $31,800
($28,200+$3,600)
ORDER FILLING
Equipment depreciation (0.60 : 0.10 : 0.30)
Order filling=$47,000 x 0.10 = $4,700
Supervisory expense (0.60 : 0.20 : 0.20)
Order filling=$6000 x 0.20 = $1,200
Total $5,900
($4,700+$1,200)
Second step is to calculate the Assign overhead costs to products:
Assign overhead costs to products:
Machining= $31,800 ÷ 10,000 MHs
Machining= $3.18 per MHOrder
Order Filling=$5,900 ÷ 1,000 orders
Order Filling = $5.90 per order
Now let calculate the Overhead cost for Product C9
Machining= $3.18 per MH × 6,900
Machining=$21,942
Order Filling= $5.90 per order × 200 Orders Order Filling=$1,180
TOTAL $23,122
($21,942+$1,180)
Therefore the overhead cost assigned to Product C9 under activity-based costing is $23,122