Answer:
e. None of the above
Explanation:
The taxable asset purchases allows the individual to increase or step up the tax basis of acquired assets so as to reflect the price of the purchases made.
If one buy an assets, then he or she wants to allocate total purchase price in a way which gives a favorable postacquisition tax results.
In case of taxable asset purchases, the tax credits or the net operating losses cannot be transferred from the target firm to the acquiring firm.
<span>Normally if one tecnician takes 475 seconds to assemble one air rule smartphone.
Then it would take. 20 technicians X secs to do the same
So It would take 20 tecnicians X secs = (20 * 475) / 1 = 9500 secs. I. e it takes 20 technicians 9500 secs to manufacture a smartphone.
But airrules uses 20 technicians to manufacture the same phone in only 30 secs.
So its efficiency would be: Number of secs it takes the 20 techician to manufacture the phone * efficiency = Normal of hours it would usually take 20 techician to manufacture the phone.
So we have 30 * X = 9500
X = 9500/30 = 316.777. So they are 316.667 times as efficient.</span>
Answer:
$774 unfavorable
Explanation:
The computation of the direct material quantity variance is shown below:
= Standard Price × (Standard Quantity - Actual Quantity)
= $8.60 × (1,910 kilograms - 2,000 kilograms)
= $8.60 × 90 kilograms
= $774 unfavorable
Since it is unfavorable as it derives that actual quantity is more than the standard quantity and in the case of favorable, the actual quantity is less than the standard quantity
Answer:
The actual labor rate per hour is $12
Explanation:
First and foremost, we need to understand that a direct labor spending variance of $990(unfavorable) means that the firm spent an additional $990 compared to what was expected.
Also, the spending variance is computed as the actual labor rate minus the standard labor rate multiplied by the actual labor hours worked
spending variance=(actual labor rate-standard labor rate)*actual labor hours
spending variance=$990
actual labor rate=unknown=(assume it is X)
standard labor rate=$11
actual labor hours worked=990
$990=(X-$11)*990
$990/990=X-$11
$1=X-$11
X=$1+$11
X=actual labor rate=$12