Answer:
d. 15
Step-by-step explanation:
Putting the values in the shift 2 function
X1 + X2 ≥ 15
where x1= 13, and x2=2
13+12≥ 15
15≥ 15
At least 15 workers must be assigned to the shift 2.
The LP model questions require that the constraints are satisfied.
The constraint for the shift 2 is that the number of workers must be equal or greater than 15
This can be solved using other constraint functions e.g
Putting X4= 0 in
X1 + X4 ≥ 12
gives
X1 ≥ 12
Now Putting the value X1 ≥ 12 in shift 2 constraint
X1 + X2 ≥ 15
12+ 2≥ 15
14 ≥ 15
this does not satisfy the condition so this is wrong.
Now from
X2 + X3 ≥ 16
Putting X3= 14
X2 + 14 ≥ 16
gives
X2 ≥ 2
Putting these in the shift 2
X1 + X2 ≥ 15
13+2 ≥ 15
15 ≥ 15
Which gives the same result as above.
Answer:
All are positive, and point upwards. The angle that they increase along the horizontal axis is different.
Step-by-step explanation:
There are no negative signs that the x is multiplied in any of the equations, and the number they are multiplied by is different for each graph: one is 1, another is 2, and the last is 3.
Number of visits can be only a whole number, the solution should be 9 visits
Answer:
9.6
trust me I double checked and everything
13x=8x+25
5x=25
X=5
5 is the answer