Answer:
Predetermined manufacturing overhead rate= $14.8 per machine hour
Explanation:
Giving the following information:
Factory 1
Estimated factory overhead= $18,500,000
Estimated machine hours for year 1,250,000
T<u>o calculate the predetermined manufacturing overhead rate we need to use the following formula:</u>
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= 18,500,000/1,250,000
Predetermined manufacturing overhead rate= $14.8 per machine hour
<span>Question number q 5.8: a company has a policy to sell goods on account with terms of 2/10, n/30. if a customer purchased $100 of merchandise from this company for cash instead of on account, the customer would pay</span>
Answer:
D) Expected purchase price of each product.
Explanation:
According to my research a "Sales Budget" is a companies estimation of sales for any given financial period of the year. This being the case we can say that the item that is NOT needed would be the expected purchase price of each product. This is because they already have the overall expenses for that period, and in a sales budget they just need to calculate the selling price and units expected to sell in order to estimate the profit.
I hope this answered your question. If you have any more questions feel free to ask away at Brainly.
Having a good credit score
Answer:
Credit of $80,000
Explanation:
Big-Mouth Frog Corporation Calculation for Retained earnings
Using this formula
Retained earnings =Revenue- Expenses
Where,
Revenue =$200,000
Expenses =$180,000
Let plug in the formula
Retained earnings =$200,000-$180,000
Retained earnings =$80,000
Therefore when the Income Summary is closed to Retained Earnings, the amount of the credit to Retained Earnings will be $80,000