A. True is the answer
Hope I helped
Answer:
Correct option is (a), Different copyright rules for pre and post 1978 works
Explanation:
Copyright is a right given exclusively a person who has created a new work and reproduce it for a stipulated time. It is granted for a stipulated time period.
For all creations after 1978, copyright is granted for the years that the creator live and seventy years after his life.
For creations before 1978, that were not published, same rules are applicable as of post 1978 period. However, for works published before 1978, copyright was granted for total 95 years that is divided between 28 years from the date of registration of work and renewed for 67 years on expiry.
So copyright rules differ for works published pre and post 1978.
I believe that the answer to the question provided above is that <span>the social trend of consuming is causing consumers to question whether or not firms are truly operating with consideration for the environment or simply changing marketing efforts in order to appear that they are.</span>
Hope my answer would be a great help for you. If you have more questions feel free to ask here at Brainly.
As a proficient customer service professional, the first step to take in such a situation is to first apologize in the kindest way possible to the customer. It would give the customer comfort to know that the server is corrected immediately while taking charge of the clients order.
<h3>What procedure is outlined above?</h3>
The above procedure is known as conflict resolution under customer care service.
One additional step maybe to keep the costumer company and ensure that they are happy before they leave.
Learn more about customer service at;
brainly.com/question/1286522
#SPJ1
The correct answer is A; Change in project scope.
Further Explanation:
The project has now changed drastically from Beta tapes to VHS. With this happening, all of the work they had did on the Beta tapes is now null. The company will now have to change the scope of their work to working with VHS tapes.
A few of the things that will have to be done to change the scope of project are;
- quality can be changed or modified
- new costs
- new tasks
- new deadlines
- more money needed to invest
- functions
Learn more about project scopes at brainly.com/question/13234457