First, we convert it into a unit like this
20 workers × 30 days = 600 units work
After leaving the 5 workers, we have 35 days to complete the work.
In 35 days only 15 workers will do the work.
So the work completed in 35 days by 15 workers = 35 ×15 =525 units
Remaining unit = 600 -525 =75 units
This unit would do by 5 workers in (75/5) = 15 days.
So after 15 days, 5 workers should leave the job.
Answer:
R { - 6, 6 }
Step-by-step explanation:
To find the range substitute the values of x from the domain into f(x)
f(- 1) = - 4(- 1) + 2 = 4 + 2 = 6
f(2) = - 4(2) + 2 = - 8 + 2 = - 6
Range { - 6, 6 }
Wait, this is simplified because there are no common terms.
Answer:
slope: -1/2
y-intercept: -2
Step-by-step explanation:
f(x) = mx+b
m is slope
b is the y-intercept
so
if f(x) = -1/2x - 2
then
the slope or m is -1/2
and the y-intercept or b is -2
R = 25 cm = 0.25 m
α = 2.00 rad /s²
T(heta) = 4 π
ω = T(heta)/ t
ω = α t
α t = 4 π / t
t ² = 2 π
t = √ ( 2π ) = 2.5 s
ω = α t = 2 · 2.5 = 5 rad/s
v = ω r = 5 · 0.25 = 1.25 m/s
(1) a (rad) = ω² r = 25 · 0.25 = 6.25 m/s²
(2) a (rad) = v² / r = ( 1.25 )² / 0.25 = 0.15625 / 0.25 = 6.25 m/s²