Answer:
Predetermined manufacturing overhead rate= $8.3 per machine hour
Explanation:
Giving the following information:
Total machine-hours 80,000
Total fixed manufacturing overhead cost $416,000
Variable manufacturing overhead per machine-hour $ 3.10
<u>First, we need to calculate the predetermined overhead rate:</u>
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= (416,000/80,000) + 3.1
Predetermined manufacturing overhead rate= $8.3 per machine hour