Answer:
6.75%
Explanation:
Data provided in the question:
Beta of the stock = 1.12
Expected return = 10.8% = 0.108
Return of risk free asset = 2.7% = 0.027
Now,
Since it is equally invested in two assets
Therefore,
both will have equal weight = = 0.5
Thus,
Expected return on a portfolio = ∑(Weight × Return)
= [ 0.5 × 10.8% ] + [ 0.5 × 2.7% ]
= 5.4% + 1.35%
= 6.75%
Answer:
No, as the net present value comes in negative
Explanation:
As we know that
Net present value = Present value of cash inflows - Initial investment
where,
Present value os $163,000
And, the initial investment is $180,000
Now placing these values to the above formula
So, the net present value is
= $163,000 - $180,000
= -$17,000
Therefore the company should not accept the project as net present value is in negative that is -$17,000