0.1241.
Step-by-step explanation:
So, from the question we are given the following parameters or information or data which are going to help us in solving this particular question/problem. They are; [1]. The critical path for a project = 37 days, the variances total or variance of critical path or sum of variance on critical path]². = 27, the desired completion time/day = 43 days.
So, we will be making use of the formula given below;
The number of standard deviation = desired completion time/day - critical time or sum of critical path times ÷√[variance of critical path or sum of variance on critical path]².
The number of standard deviation = 43 - 37 ÷ √27 = 1.1547.
Thus, the probability of completing in 43 days = P(Z > 1.1547) = 0.1241.
In this case, it's clear that 5 is half of ten, therefore, you have to divide the first equation in half, giving you 5x42= 210. If it was something such as 20x24, you just work the answer from the multiple of ten.
Hope this helpsn
(2x - 5)° + 45° = 180°
2x° + (-5 + 45)° = 180°
2x° + 40° = 180°
2x° = 180° - 40°
2x° = 140°
x° = 140 ÷ 2
x° = <u>7</u><u>0</u><u>°</u>
So, the value of x is 70°
<em>Hope it helps and is useful</em><em> </em><em>:</em><em>)</em>