Answer:
Product development
Explanation:
A manufacturer tests, modifies, and retests an original idea several times before offering it to the consumer. This process is called product development.
A product life cycle can be defined as the stages or phases that a particular product passes through, from the period it was introduced into the market to the period when it is eventually removed from the market.
Generally, there are four (4) stages in the product-life cycle;
1. Introduction.
2. Growth.
3. Maturity.
4. Decline.
I believe the correct answer is the first option. The labor supply curve is upward sloping because the opportunity cost of leisure decreases as wages decrease and the opposite of such is true as well. As one work one hour more, one will have less time for other activities. As the work rate increases in value, then the opportunity cost increases as well.
In a bottom-up approach, managers should have a high level of controllability and a high level of involvement in budget setting.
<h3>What is a bottom-up budget approach?</h3>
- Bottom-up budgeting is a method of creating budgets that begins at the departmental level and works its way up.
- Each department within the organization must create a list of the supplies it requires, the projects it intends to complete throughout the upcoming fiscal year, and cost projections.
<h3>What is top-down and bottom-up budgeting?</h3>
- Departments must create budgets in top-down planning while adhering to the limitations imposed by senior leadership.
- Departments produce their own budget estimates and submit them to top leadership in a bottom-up budget.
- The two strategies are the two types of budgeting that are most frequently used.
<h3>What is bottom-up approach in accounting?</h3>
- Bottom-up forecasting is a technique for predicting an organization's future performance by beginning with basic company information and moving "up" to revenue.
- This strategy begins with thorough customer or product data before expanding to revenue.
Learn more about bottom-up approach here:
brainly.com/question/19672423
#SPJ4
Answer:
Machine A = $ 1.22 million
Machine B = $ 0.70 million
Explanation:
The Equivalent Annual Annuity of the machines is as follows
Machine A = $ 1.22 million
Machine B = $ 0.70 million
Thus the Machine A with a higher Equivalent Annual Annuity of $ 1.22 Million is the better machine.
If the company accepted the better machine which is Machine A, the value of the company increases by $ 3.57 Million (Which is the net total of discounted cash Inflows = Net Present value of Machine A)
See attached file for details.
When the project risk is 30%, and its occurrence leads to a change in the project budget by around 10%, then the risk score is 0.03.
<h3>What is a risk score?</h3>
The result of multiplication of the risk impact on the budget by the probability of occurrence of the risk, is known as the risk score. Using the given information, it can be calculated as,
Hence, option B holds true regarding the risk score. The complete question is added in the image for reference.
Learn more about risk score here:
brainly.com/question/27181888
#SPJ1