Answer:
Fourth option: 30 days
Step-by-step explanation:
We three path to complete the project:
Path A:
A1 → A2 → A3
10 days → 8 days → 9 days = 27 days
Path B:
B1 → B2 → B3
2 days → 7 days → 3 days = 12 days
Path C:
C1 → C2 → C3
10 days → 8 days → 12 days = 30 days
Then the duration of the critical path is 30 days, we can't conclude the project until each path has finished
Answer:
O is the center of the circle with radius IE(=ID=EF)
Step-by-step explanation:
Join all 3 points D, E, F, forming the triangle DEF.
Let the midpoint of EF be M and the midpoint of ED be N. (first picture)
Join point I to E, D and F.
Since IN is both an altitude and median to triangle EID, then triangle EID is an isosceles triangle, and IE=ID
similarly, we see that IE=IF.
conclusion: IE=ID=EF.
Answer:
x = 1
y = 5
Step-by-step explanation:
x + y = 4 __ (1)
2x + y = 3 __ (2)
equation (1) x 2, (2) x 1
2x + 2y = 8
2x + y = 3
0 + y = 5
y= 5 (ANS)
x + y = 4
x + 5 = 4
x = 5 - 4
x = 1 (ANS)
I HOPE MY ANSWER IS CORRECT IF NOT I APOLOGIZE.