Answer:
The main advantage of the discounted payback period method is that it can give some clue about liquidity and uncertainly risk. Other things being equal, the shorter the payback period, the greater the liquidity of the project. Also, the longer the project, the greater the uncertainty risk of future cash flows.
Answer: $225,000
Explanation:
Given that,
Company acquired a mine = $970,000 of this amount,
Land value = $100,000 and remaining portion to the minerals in the mine
Ore appear to be in the mine = 12,000,000 units
Aristotle incurred development costs = $170,000
fair value of its obligation = $40,000
ore were extracted = 2,500,000 units
Units sold = 2,100,000
=
= $0.09 depletion per unit
The total amount of depletion for 2017 = depletion per unit × ore were extracted
= $0.09 × 2,500,000
= $225,000
Adding all of that would equal to $1,346