<span>the real exchange rate is greater than one and arbitrageurs could profit by buying oranges in Morocco and selling them in the U.S.</span>
Answer: d. a misrepresentation of a fact knowing it is falso
Explanation:
Reliance that gives rise to liability for fraud requires intentional misrepresentation, that is a misrepresentation of a fact knowing that it is false. If Ness, the broker intentionally misled Ollie and advised Ollie to buy Penny stock shares based on Ness's that the stock price will rise Ness will be charged with fraud.
Answer:
Glocalisation
Explanation:
Thirst, a beverage manufacturer is involved in glocalisation by marketing its products using the same strategy globally. However, the ethnicity contained in their ads and the music used in jingles change according to the place. This is to say that they make use of ads which is particular to a specific location taking their culture and language into consideration.
The term "glocalization" was coined by sociologist Roland Robertson in the Harvard Business Review, in 1980.
Glocalization is a combination of the words "globalization" and "localization".
Glocalization is used to describe the ability of a product or service that is developed and distributed worldwide to adjust and accommodate the consumer in a local market.
Consumers in the local market have different taste and preference. Glocalisation is the ability of a product sold globally to fit into the local market at different places. It is an expensive process but firms usually make more benefits from practicing glocalisation.
Answer:
Explanation:
Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?
Since B is the predecessor of C.
Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B +Duration of C).
Represent
Run = R
Duration of A = DA
Duration of B = DB
Duration of C = DC
Project Completion time = PT
<u>R DA DB DC PT</u>
1 51 48 17 48 + 17 = 65
2 60 48 19 48 + 19 = 67
4 31 48 22 48 + 22 = 70
5 30 31 14 31 + 14 = 45
6 41 16 17 41
7 44 12 6 44
8 44 12 10 44
9 45 43 9 43 + 9 = 52
10 60 41 10 60
<u> Total = 546</u>
Total Project completion time in 10 Stimulations = 546
Average project Completion time = 546/10 = 54.6
Therefore, average Project completion time is between 53 and 56 days.