Answer:
(a) $3,160
(b) $7,000
(c) $13,500
(d) $9,500
(e) $2,960
Explanation:
(a). Work in Process = Manufacturing cost of 103 in June + Manufacturing cost of 104 in June
Work in Process = $960 + $2,200 = $3,160
(B). Finished goods = Manufacturing cost of 101 in June + Manufacturing cost of 102 in June
Finished goods = $3,800 + $3,200 = $7,000
(C) Cost of goods sold during July = Manufacturing cost of 101 in June + Manufacturing cost of 102 in June + Manufacturing cost of 104 in June + Manufacturing cost of 104 in July
Cost of goods sold during July = $3,800 + $3,200 + $2,200 + $4,300 = $13,500
(D) Work in process inventory = Manufacturing cost of 105 in July + Manufacturing cost of 106 in July
= $6,200 + $3,300 = $9,500
(E) Finished goods inventory = Manufacturing cost of 103 in June + Manufacturing cost of 103 in July
Finished goods inventory = $960 + $2,000 = $2,960