A construction manager needs 12 workers to complete a building project in 54 days, we can write;
12 workers = 54 days
T find the number of workers needed to complete the same project in T days, we will write;
x workers = T days
Divide both equations
12/x = 54/T
Cross multiply
12T = 54x
x = 12T/54
x = 2T/9
Hence the number of workers needed to complete the same project in T days is 2T/9 workers
<u><em>Answer:</em></u>
The bird will have traveled 403 meters in 13 seconds if it maintained a speed of 31 m/sec
<u><em>Explanation:</em></u>
<u>The equation that relates velocity, distance and time is:</u>
<u>This means that:</u>
distance = velocity * time
<u>In the given, we have:</u>
velocity = 31 m/sec
time = 13 sec
<u>Substitute with the givens in the above equation and solve for the distance as follows:</u>
distance = velocity * time
distance = 31 * 13
distance = 403 meters
Hope this helps :)
2.5x-8=5x+12
-2.5x -2.5x
--------------------
-8=2.5x+12
-12 -12
--------------------
-20 = 2.5x
------ ------
2.5 2.5
x=-8