Answer:
cost of goods manufactured= $788,400
Explanation:
Giving the following information:
Cost of direct materials used in production $280,000
Direct labor 324,000
Factory overhead 188,900
Work in process inventory, April 1 72,300
Work in process inventory, April 30 76,800
<u>To calculate the cost of goods manufactured, we need to use the following formula:</u>
cost of goods manufactured= beginning WIP + direct materials + direct labor + allocated manufacturing overhead - Ending WIP
cost of goods manufactured= 72,300 + 280,000 + 324,000 + 188,900 - 76,800
cost of goods manufactured= $788,400