Answer:
Amount of overhead applied is $270
correct option is (a) $270
Explanation:
given data
overhead cost = $105,000
overheat rate = $3 per machine hour
manufacturing overhead = 70000 machine hour
required = 60 machine hours
to find out
The amount of overhead applied to Job P 233 is closest to
solution
we find manufacturing overhead rate here that is
manufacturing overhead rate =
put here value
manufacturing overhead rate =
manufacturing overhead rate = 1.5 per machine hour
and
Total manufacturing overhead rate will be for overheat rate $3
Total manufacturing overhead rate = (3 + 1.5) = $4.5 per machine hour
so we can say that Amount of overhead is job P 233 is
Amount of overhead applied = 60 × $4.5 = 270
so here correct option is (a) $270