Answer:
For 1,000 bricks, the amount charged will be the same
Step-by-step explanation:
Let the number of bricks for which they charge the same amount be $x
Thus;
The total cost from the first company will
be;
250 + 0.2(x) = 250 + 0.2x
The second will charge;
400 + 0.05(x) = 400 + 0.05x
Since the amount charged will be equal at x bricks, we need to equate both;
400 + 0.05x = 250 + 0.2x
400-250 = 0.2x-0.05x
150 = 0.15x
x = 150/0.15
x = 1,000