Answer:
Total direct labor variance= $960 favorable
Explanation:
Giving the following information:
We will separate the direct labor cost variance in rate and quantity variance. <u>To calculate the direct labor rate and quantity variance, we need to use the following formulas:</u>
Direct labor time (efficiency) variance= (Standard Quantity - Actual Quantity)*standard rate
Direct labor time (efficiency) variance= (30*6 - 130)*14
Direct labor time (efficiency) variance= $700 favorable
Direct labor rate variance= (Standard Rate - Actual Rate)*Actual Quantity
Direct labor rate variance= (14 - 12)*130
Direct labor rate variance= $260 favorable
Actual rate= 1,560/130= $12
Total direct labor variance= 700 + 260
Total direct labor variance= $960 favorable