Answer:
Collection from Customers =$487,000
Explanation:
Collection from Customers=account receivable beginning balance+sales revenue-account receivable ending balance
=97000+$519,000-$65,000
=$487,000
Answer:
B. primary activity
Explanation:
Based on the information provided within the question it can be said that in this scenario North Star is addressing a primary activity in the value chain analysis. This is because the five primary activities are inbound logistics, operations, outbound logistics, marketing and sales, and service. So in this scenario, North Star implementing new equipment into its production it is dealing with the operations factor of the primary activities.
Answer:
The correct answer is letter "C": usage of the most abundant factors of production, while the focus of the comparative advantage theory is on the productivity of the production process.
Explanation:
The Factor Productions theory, also known as the <em>Heckscher-Ohlin</em> theory, is a concept that tries to explain how international trade works. It is based on the focus that production increases capital and labor to an equal importance level. While, the Comparative Advantage theory is defined as the ability of an individual, company, or country to produce a good or service at a lower opportunity cost than its competitor.
Answer:
The amount of interest is $576.
Step by step explanation :
Given : Enrique borrowed $3600 to put a down payment on a motorcycle. The loan had a simple interest rate of 8% for 2 years.
To find : The amount of interest he will pay on the loan.
Solution : Using the formula,
Where, I= Interest , P=principal , R= rate, T=time in years
We have given that :
P=$3600
R=8%=0.08
T=2 years
Substitute value in the formula to find interest,
Therefore, The amount of interest is $576.
Answer:
$12000 ( A )
Explanation:
Calculate The minimum cost to crash this project by 2 weeks
To get the minimum cost to crash this project in 2 weeks we have to first look to crash the activity on the critical path that has the lowest cost of crashing from the first week
critical path: A-B-D-F-G = 25 weeks
After crashing Activity B by 1 week both paths become critical paths hence we need to crash activity C and D by 1 week each so that the paths can crash simultaneously within 2 weeks
therefore the overall crash cost for 2 weeks will be
crash costs of Activities : B + C + D ( 1st crashes)
= 3500 + 4000 + 4500
= $12000