Answer:
17.19 years
Explanation:
The triple value of the earnings per share=$3.50*3=$10.50
The growth rate is 6.6%
Using the nper formula in excel, we can determine the number of years earnings per share would triple
=nper(rate,pmt,-pv,fv)
rate is 6.6%
pmt is not applicable to the scenario ,hence it is zero
pv is the current earnings per share
fv is the future earnings per share
=nper(6.6%,0,-3.5,10.5)= 17.19
Answer:
A.$141.80
Explanation:
Present Value of Trish payments =
Present Value of Trish payments = $450 + $450
Present Value of Trish payments = $180,54
Present Value of Josh payments =
Present Value of Josh payments = $450
Present Value of Josh payments = $17,912
Difference between two payments = 18054 - 17912 = 141
The cycle of money where it results to profits for business
and salaries for workers are when we pay money for the services or things that
we buy and this ends when we receive the items and services we need. Cash
conversion is also another term for this cycle.
Answer:
Reserves
Explanation:
Risk is any uncertain event with positive or negative consequences on a project. Contingency costs are related to risks, and therefore cannot be disregarded in risk management within a project. It is essential that management plan and prevent for the project to occur in a predictable and effective manner.
Answer: A. deferred and recognized as income over the term of the lease.
Explanation:
In a sale-leaseback transaction, that is when a property is sold by a company and leased back, the property seller is the lessee and the property purchase is the lessor. In this case, a sale-leaseback will allow a company to sell an asset so that the company can raise capital, after which the asset can then be leader back.
When a company sells property and then leases it back, any gain on the sale should usually be deferred and recognized as income over the term of the lease.