Answer:
Cost Variance (CV) for the project is negative $77.5
Explanation:
The total amount budget for all 3 activities = Activity A worth $200 + Activity B worth $75 + Activity C worth $200 = $475
The total value completed = activities cost x % complete = $200*100% + $75*90% + $200*75% = $417.5
The actual cost till now = $200 + $120 + $175 = $495
The cost variance = The total value completed - The actual cost till now = $417.5 - $495 = ($77.5)
I think the answer is b. Sorry if it isn't it is just a guess.
Answer: e) $6,506.04
Explanation:
Employees do not pay FUTA or SUTA. Employers pay those.
Ms. Grant's net pay for the month therefore is;
= Gross earnings - FICA Social Security - FICA Medicare - Federal Income tax withheld
= 8,588 - (6.2% * 8,588) - ( 1.45% * 8,588) - 1,424.97
= 8,588 - 532.46 - 124.53 - 1,424.97
= $6,506.04
It’s important for your future. So you won’t be some kind of debts. It’s always better to plan rather than doing things last minute.
Answer:
The correct answer is letter "C": two-part pricing.
Explanation:
Two-part pricing is set when there is a fixed price for a good or service but there is a variable price added based in a charge per unit of consumption. The sum of the two prices is the total the consumers have to pay to access the product. Typically, this type of pricing is set in monopolistic markets.