Answer:
Variable cost per unit= $50
Fixed costs= $900,000
Explanation:
Giving the following information:
Total Costs Units Produced
January $1,900,000 20,000 units
February 2,250,000 27,000
March 2,400,000 30,000
<u>To calculate the unitary variable cost and the fixed cost under the high-low method, we need to use the following formulas:</u>
<u></u>
Variable cost per unit= (Highest activity cost - Lowest activity cost)/ (Highest activity units - Lowest activity units)
Variable cost per unit= (2,400,000 - 1,900,000) / (30,000 - 20,000)
Variable cost per unit= $50
Fixed costs= Highest activity cost - (Variable cost per unit * HAU)
Fixed costs= 2,400,000 - (50*30,000)
Fixed costs= $900,000
Fixed costs= LAC - (Variable cost per unit* LAU)
Fixed costs= 1,900,000 - (50*20,000)
Fixed costs= $900,000