Answer:
the total setup time of this process is 100 minutes
Explanation:
Given the data in the question;
Vat holds up to 1000 gallons;
Rate of chemical agents being added to the vat = 4.5 gpm
Reaction time = 85 minute
cleaning ( waiting time ) 15 minute
the setup time of this process = ?
To calculate the setup time for this process, we simply say;
the setup time = Reaction time + cleaning ( waiting time )
so we substitute in our values
the setup time = 85 mins + 15 mins
the setup time = 100 minutes
Therefore, the total setup time of this process is 100 minutes