Answer:
C. Create a rotating assignment so each team member shares note taking.
Explanation:
In the case noted in the question above, there is a situation that could be unpleasant if it were decided by some type of bias.
Therefore, the most appropriate alternative for the team to address this situation would be to create a rotating assignment for each team member to share the notes. This way it would not happen that a team member is always chosen to perform a task that causes dissatisfaction in the whole team. Creating a rotating assignment to carry out the task would guarantee the uniformity of the task assignment and avoid possible dissatisfactions, inequalities and interpersonal conflicts that could arise.
The price elasticity of the bond, based on the years to maturity and the required rate of return is -0.494
<h3>How to find the price elasticity of he bond?</h3><h3 />
First, find the new price of the bond:
= 1, 000 / ( 1 + 15%)⁵
= $497
The change in price:
= (497 - 567) / 567
= -12.3%
Then find the percentage change in the required rate of return:
= (15 - 12%) / 12
= 25%
The price elasticity of the bond is:
= -12.3% / 25%
= -0.494
Find out more on price elasticity at brainly.com/question/5078326
#SPJ1
While figuring out how to save money for a bride who is having financial problems, Paula, the catering manager of Oh Happy Day, asked her assistant, "What do you think is the best menu to offer under these particular circumstances? How can we offer the bride and groom's guests a great meal within their budget?" Paula and her assistant are using the contingency approach.
True
EcoMart establishes General Journal
May 2
Dr Petty cash 1050
Cr Cash 1050
May 30
Dr Merchandise inventory 120
Dr Postage expense 359
Dr Miscellaneous expenses 240
Dr Cash short and over 9
Cr Cash728
June 1
Dr Petty cash 150
Cr Cash 150
Workings:
May 30,Merchandise inventory 120+ Postage expense 359+ Miscellaneous expenses 240+ Cash short and over 9 = $728
June 1
1050-1200= 150
Answer:
If an activity has a slack value greater than zero, it needs to be a critical activity
Explanation:
The false statement in the group of answer choices is If an activity has a slack value greater than zero, it needs to be a critical activity this is because for an activity to be considered a critical activity its slack value has to be equal to zero and not greater than zero,
activities with critical value greater than zero are considered just activities and not critical activities because there is time range given to the activity