Question Completion:
A manufactured product has the following information for June.
Standard Actual
Direct materials 6 lbs. at $8 per lb. 48,500 lbs. at $8.10 per lb.
Direct labor 2 hrs. at $16 per hr. 15,700 hrs. at $16.50 per hr.
Overhead 2 hrs. at $12 per hr. $198,000
Units manufactured 8,000
Answer:
Direct materials price variance = $4,850 U
Direct materials quantity variance = $4,000 U
Explanation:
a) Data and Calculations:
Actual Standard
Direct materials price per lbs $8.10 $8.00
Direct labor rate per hour $16.50 $16.00
Quantity:
Direct materials 48,500 48,000 (6 * 8,000)
Direct labor hours 15,700 16,000 (2 * 8,000)
Direct materials price variance = SP - AP * AQ
= $8 - $8.10 * 48,500
= $0.10 * 48,500
= $4,850 U
Direct materials quantity variance = SQ - AQ * SP
= 48,000 - 48,500 * $8
= $4,000 U