Answer:
the data regarding output and the quantity of labor is missing, so I looked for a similar question and found the attached image.
if one employee is hired, total production = $80, and total cost = $55
if two employees are hired, total production = $150, and total cost = $110
if three employees are hired, total production = $210, and total cost = $165
if four employees are hired, total production = $260, and total cost = $260
hiring <u>four employees</u> should maximize profits since MC = MR