Answer:
Estimated manufacturing overhead rate= $39 per machine hour
Explanation:
Giving the following information:
Estimated machine-hours= 20,000
The estimated variable manufacturing overhead was $9 per machine-hour.
The estimated total fixed manufacturing overhead was $600,000.
To calculate the estimated manufacturing overhead rate we need to use the following formula:
Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Estimated manufacturing overhead rate= (600,000/20,000) + 9
Estimated manufacturing overhead rate= $39 per machine hour