Answer: $245
Explanation:
If the required return on the stock is 7 percent, the current share price would be calculated as:
= 6.60/1.07 + 17.60/1.07^2 + 22.60/1.07^3 + 4.40/1.07^4 + [(4.4 × 1.0525) / (7%-5.25%)] / 1.07^4
= $245.23
= $245 approximately
Therefore, the current share price will be $245
Answer: Po = Do(1+g)/Ke-g
Po = $3.10(1-0.109)/0.13 - (-0.109)
Po = $3.10(0.891)/0.13+0.109
Po = $3.10(0.891)/0.239
Po = $11.56
Explanation: The current market price of the stock equals the current dividend paid multiplied by 1+g divided by the excess of cost of equity over growth rate. The growth rate is negative in this case, thus, the growth rate would be deducted from 1. Moreso, the growth rate will be added to cost of equity since it is negative. Thus, the amount that the investor will be willing to pay is $11.56.
Answer:
The correct answer is D. 10.00%
Explanation:
To get internal rate of return we use excel or a spreadsheet. See document attached.
Make the cash flow to solve this problem. At moment 0 we have the investment cost , in this case $1.475.668 (negative) From period 1 to period 5, we have different incomes o benefits. Salvage value is 1.615.205, we are going to get it at moment 5 (positive).
Then, we calculate the Net cash flow that is the difference between benefits and cost.
We use all the result (positive and negative) in Net cash flow to get the IRR.
Net Present Value (NPV) 768907
Internal Rate of Return (IRR) 10,00%
Answer:
The correct answer is D.
Explanation:
Giving the following information:
Units produced - Inspection cost
February: 911 - $16,812
March: 961 - $17,200
April: 917 - $16,865
May: 901 - $16,710
June: 923 - $16,894
July: 908 - $16,780
August: 925 - $16,932
September: 865 - $16,300
October: 904 - $16,738
To calculate the fixed component using the high-low method, first, we need to calculate the unitary variable cost:
Variable cost per unit= (Highest activity cost - Lowest activity cost)/ (Highest activity units - Lowest activity units)
Variable cost per unit= (17,200 - 16,300) / (961 - 865)
Variable cost per unit= $9.375 per unit
Now, we can calculate the fixed costs:
Fixed costs= Highest activity cost - (Variable cost per unit * HAU)
Fixed costs= 17,200 - (9.375*961)
Fixed costs= 8,190.625
Fixed costs= LAC - (Variable cost per unit* LAU)
Fixed costs= 16,300 - (9.375*865)
Fixed costs= $8,190.625