Answer:
time from raw materials receipt to finished product exit.
Explanation:
Manufacturing cycle time is best defined as the "time from raw materials receipt to finished product exit."
To explain better, manufacturing cycle time is the overall time of process that covers the total duration it takes the final production of commodities to be made. That is beginning from the inception stage which is usually raw materials through its conversion stage and eventually into finished goods.
Answer:
$50
Explanation:
25% = 1/4
200 / 4 = 50
50*3=150, which is 25% off.
Answer: Please refer to Explanation.
Explanation:
Two Companies. We shall call them A and B.
If A and B decide not to advertise, they both get $5,000,000.
If A advertises and B does not then A captures $3 million from B at a cost of $2 million meaning their payoff would be,
= 5 million - 2 million + 3 million
= $6 million.
A will have $6 million and B will have $2 million as $3 million was captured from them. This scenario holds true if B is the one that advertises and A does not.
If both of them Advertise, they both reduce their gains by $2 million while capturing $3 million from each other so they'll essentially both have just $3 million if they both decide to advertise.
With the above scenarios, it is better for both companies to ADVERTISE if there is NO COLLUSION. This is because it ensures that they do not get the lowest payoff of $2 million if the other company decides to advertise and they do not.
However, if they DO COLLUDE. They must both decide that NONE of them SHOULD ADVERTISE and this would leave them with their original $5 million each which is a higher payoff than the $3 million they will both receive if they were both advertising.
Answer:
The answer is "Option b".
Explanation:
In this scenario, the second option, which would be the percentage within each transaction that's also interest instead of the full amount, would've been lower if the rate of interest were lower because interest-related transactions would have been higher at lower rates and conversely, as opposed to the main refunds.
Answer:
A. III only
Explanation:
One of the very useful tools in project management analysis is the PERT and CPM.
PERT (Program evaluation and review technique) provides valuable information regarding which activities need to be closely watched.
While CPM (Critical Path Method) helps in determining the time required to complete each task, and the minimum time required to complete a project.
Both CPM and PERT serve similar purposes by helping to determine projects or activities that need to be watched closely.