Answer:
Total cost= $350,400
Explanation:
Giving the following information:
For Gundy Company, units to be produced are 5,280 in quarter 1 and 6,400 in quarter 2. It takes 2.0 hours to make a finished unit, and the expected hourly wage rate is $15 per hour.
Quarter 1:
Direct labor cost= 5,280*2= 10,560 hours
Quarter 2:
Direct labor cost= 6,400*2= 12,800 hours
Total cost= (10,560 + 12,800)*15= $350,400