Answer:
$400 favorable
Explanation:
The computation of the volume variance is shown below:
Fixed overhead Volume Variance = Actual Overheads - Budgeted Overheads
where,
Actual overhead is
= 5,200 units × 2 hours × $1
= $10,400
And, the budgeted overhead is
= 5,000 units × 2 hours × $1
= $10,000
So, the volume variance is
= $10,400 - $10,000
= $400 favorable
We simply deduct the budgeted cost from the actual cost so that the difference could be come