Answer:
$192 million; $153.60 million; $38.40 million
Explanation:
Given that,
Direct material purchased = $80 million
Direct labor costs = $51 million
Manufacturing overhead = $77 million
Percent of the work-in-process completed = 80%
(1) Transfers-In:
= Direct materials + Direct labor costs + Manufacturing overhead
= (80% × $80 million) + $51 million + $77 million
= $64 million + $51 million + $77 million
= $192 million
(2) Transfer-out:
= Transfers-In × percent of the work-in-process completed
= $ 192 million × 80 %
= $ 153.60 million
(3) Ending Balance:
= Transfers-In - Transfer-out
= $192 million - $ 153.60 million
= $38.40