Answer: Straight line PPF, Opportunity cost is constant.
Explanation:
The PPF for Sweden is downward sloping straight line which depicts that the resources that are used in the production of these two goods are not specialized and the same set of resources is equally useful in producing both smartphones and tablets. Thus, Sweden's opportunity cost of producing more smartphones and fewer tablets should remain constant.
Answer:
$480
Explanation:
Data provided in the question:
Machine Hours Repair Costs
2,400 $6,385
1,200 $3,480
2,000 $5,285
3,400 $8,980
Now,
Machine Hours Repair Costs
Highest 3,400 $8,980
Lowest 1,200 $3,480
Difference 2,200 $5,500
Unit variable cost = $5,500 ÷ 2,200
= $2.5
Total cost at high level = $8,980
Machine hours highest level = 3,400
Also,
Total cost at high level = Fixed cost + Variable cost at highest level
or
$8,980 = Fixed cost + [ $2.5 × 3,400 ]
or
Fixed cost = $8,980 - [ $2.5 × 3,400 ]
= $8,980 - $8,500
= $480
Answer: C) $2,000 per week.
Explanation:
The slope of the project refers to the additional amount that it would cost to be able to finish the project faster than schedule.
In the question, the construction activity is for 14 weeks at a rate of $5,000 for the laborers per week. If you wanted to reduce this project duration to 10 weeks, you will have to spend an additional $2,000 more per week.
This $2,000 is therefore the slope of the activity.