Answer:
76.8 minutes
Step-by-step explanation:
Every 8 cycles we have 6 regular work elements plus 1 irregular work element.
So, the normal time for 8 cycles is
3*4.25+1.75 = 14.5 minutes.
Since the PDF allowance factor is 16%, the standard time for 8 cycles is 14.5 increased 16%
14.5*1.16 = 16.82 minutes.
So, the anticipated amount of time worked every 14.5 minutes
is 2.32 minutes.
An 8-hour shift has 480 minutes = 33.1034*14.5, so the anticipated amount of time per 8-hour shift is
33.1034*2.32 = 76.8 minutes