Answer:
The correct answer is C.
Explanation:
Giving the following information:
Fixed manufacturing overhead cost of $497,000, variable manufacturing overhead of $2.40 per direct labor-hour, and 70,000 direct labor-hours.
T 498:
Total direct labor-hours 80
First, we need to calculate the estimated manufacturing overhead rate for the period:
Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Estimated manufacturing overhead rate= (497,000/70,000) + 2.4= $9.5 per direct labor hour.
Now we can allocate the overhead to Job 498:
Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base
Allocated MOH= 9.5*80= $760