Answer:
(a) 2min/15units
(b) 1min/20units
(c) The bottleneck stage is cutting. The process capacity is 450units/hour
(d) The capacity of the new employee should be 1unit/2sec. The process capacity will increase four times
Step-by-step explanation:
(a) Cycle time for stage cutting for 2 employees = 16sec/2units × 1min/60sec = 2min/15units
(b) Cycle time for stage sealing for 1 employee = 3sec/1unit × 1min/60sec = 1min/20units
(c) Process capacity of stage cutting = 15units/2min × 60min/1hour = 450units/hour
(d) If the capacity of the new employee is 1unit/2sec, the process capacity = 1unit/2sec × 3600sec/1hour = 1800units/hour. The process capacity increases 4 times (1800/450 = 4)
Answer: - 16n - 31
Step-by-step explanation:
4 - 16n - 35
Answer:
True
Step-by-step explanation:
same numbers on both sides = equivalent expression
Answer:
x=13
Step-by-step explanation:
Divide both sides by -5 then solve the equation for x
Answer:
33º and 147º
Step-by-step explanation:
x + (x + 114) = 180
2x + 114 = 180
2x = 66
x = 33º
x + 114 = 147º