Answer: $3,875 Favorable
Explanation: We can compute direct labor efficiency variance by using following formula :-
Direct labor efficiency variance = standard rate ( actual hours - standard hours)
where,
standard hours = 5,500units * 0.5 hour = 2750 hours
actual hours = 3,000 hours
standard rate = $15.5
putting the values into equation we get :-
Direct labor efficiency variance = $15.5 ( 3,000 - 2750)
= $3,875 Favorable
Answer: Corporate Cultural Responsibility.
Explanation:
The corporate cultural responsibility of a company are the standards members of the society have come to expect from the company based on the previous ways their members of staff have been seen to operate. Corporate Cultural responsibility can be seen in staff dress-code and work style.
Answer: $0.79.
Explanation:
Given that,
Tendered bill = $5
Bill charged = $4.21
Therefore,
The change due is calculated by subtracting bill charged from tendered bill.
Change due = Tendered bill - Bill charged
= $5 - $4.21
= $0.79
Hence, change in dollars would be $0.79.
Answer:
No adjustment in records can be made until the asset is sold.
Explanation:
This is an example of cost concept. Assets are generally recorded at cost and remain on the accounting records at cost until they are disposed of. Future economic condition may change this appraised value, and therefore no adjustment in records can be made until the asset is sold.
Answer: 0.050
Explanation:
Mean = 18
USL = 18.6
LSL = 17.4
SD = 1.25
Cpk = Min{(mean - LSL / 3*sd), (USL - mean / 3*sd)}
= Min{ ( 18 - 17.4/ 3 * 1.25), (18.6 - 18 / 3 * 1.25)}
= Min { 0.05 0.05)
Cpk = 0.050