Answer:
c) finish-to-start; start-to-start
Explanation:
Project dependencies are the time relationships between a predecessor and a successor in project management. In other words, these dependencies describe which activity among the two needs to start earlier or later and when it needs to start or finish compared to the other one.
The most common type of dependency in all projects (no matter the nature or industry) is the finish-to-start one, where the activity A needs to be completed before activity B starts, e.g. base nail polish has to be put before the top coat gets put on the nails.
The second most common type of dependency is the<em> start-to-star</em>t one, where two activities need to start at the same time. This is common for activities where synchronization is paramount.
Answer:
B) a local cable company
Explanation:
A local cable company provides communication services using underground cables. Service offed by a cable company includes televisions, internet connectivity, and telephone services. Such a company needs communication equipment to facilitate signal and message transmission.
Damien repairs communication equipment. He probably works for a local cable company.
Answer:
Explanation:
The journal entries are shown below:
a. Artwork A/c Dr $85,500
To Cash A/c $85,500
(Being work is reported on the government-wide financial statements)
Depreciation Expense A/c Dr $5,700
To Accumulated Depreciation A/c $5,700
(Being depreciation expense is recorded)
The depreciation expense is shown below:
= Original cost ÷ useful life
= $85,500 ÷ 15 years
= $5,700
b. Artwork expenditure A/c Dr $85,500
To Cash A/c $85,500
(Being work is reported on the fund financial statements