Answer:
Unitary cost= $30
Explanation:
Giving the following information:
Material costs for a selected job are $900 for a batch of 30 suit coats (units).
<u>To calculate the unitary cost, we need to use the following formula:</u>
unitary cost= total batch cost / number of units
unitary cost= 900 / 30
unitary cost= $30
Incurring actual indirect factory wages in excess of budgeted amounts for actual production results in a controllable variance. Therefore, the option B holds true.
<h3>What is the significance of controllable variance?</h3>
Controllable variance can be referred to or considered as a variance that computes the difference between the actual quantity and the budgeted quantity sold or consumed by a firm in an economy. It can never be deficit, and is always in surplus of the budgeted amounts.
Therefore, the option B holds true and states regarding the significance of controllable variance.
Learn more about controllable variance here:
brainly.com/question/13985361
#SPJ4
The question seems to be incomplete. It has been added below for better reference.
Incurring actual indirect factory wages in excess of budgeted amounts for actual production results in a:
a. quantity variance
b. controllable variance
c. volume variance
d. rate variance
Energizer emphasizes the importance of a relationship marketing. Why? Relationship marketing builds brand loyalty, interaction and long-term engagement from consumers. Energizer used this method from the beginning wanting to connect with their audience and build one-on-one relationships. The Energizer Bunny came about to promote their brand and customers connected and now recognize the Bunny as part of Energizer.