The work done by Joe is 0 J.
<u>Explanation</u>:
When a force is applied to an object, there will be a movement because of the applied force to a certain distance. This transfer of energy when a force is applied to an object that tends to move the object is known as work done.
The energy is transferred from one state to another and the stored energy is equal to the work done.
W = F . D
where F represents the force in newton,
D represents the distance or displacement of an object.
Force = 0 N, D = 20 cm = 0.20 m
W = 0 0.20 = 0 J.
Hence the work done by Joe is 0 J.
Answer:
Newton's second law
Explanation:
The relationship between mass and acceleration is described in Newton's Second Law of Motion. His Second Law states that the more mass an object has, more force is necessary for it to accelerate.
<span>C. Mao Zedong
Hope this helps!~</span>
Answer:
the speed of the satellite is 12,880.53 km/h
Explanation:
Given;
radius of the circular orbit, r = 24,600 km
time taken to revolve around Earth, t = 12 hours
The circumference of the satellite is calculated as;
L = 2πr
L = 2π x 24,600 km
L = 49,200π km
L = 154,566.36 km
The speed of the satellite;
v = L/t
v = 154,566.36 / 12
v = 12,880.53 km/h