Giving the following information:
Direct materials standard (4 pounds @ $1/lb.) $4 per unit
Direct materials flexible budget variance—unfavorable $15,000
Actual direct materials used 103,000 pounds
Actual units produced 22,000 units
Direct material quantity variance= (standard quantity - actual quantity)*standard price