Answer: No.
Step-by-step explanation:
9*7=63
63+7=70
70>73
I would try and help but I think it's missing the picture
The expected activity time for the given statement is = 5.33
<h3>What time is the PERT network expected to be active?</h3>
The average amount of time required for an activity when it is repeatedly performed is known as the expected time. The weighted average of the three estimated times, i.e., the optimistic time, the most probable time, and the pessimistic time, is used in project management analysis to determine the expected time of activity.
<h3>The PERT system:</h3>
A network model called the Program Evaluation and Review Technique (PERT) allows for randomness in the timing of activity completion. PERT was created in the late 1950s again for a massively labor-intensive Polaris project for the US Navy. It might shorten a lot of time and cost needed to finish a project.
<h3>According to the given information:</h3>
optimistic = 2
most likely = 5
pessimistic = 10.
We will use the following formula to calculate the anticipated time for each activity in order to solve this problem:
Expected Time = (Optimistic Time + (4 x Most likely) + Pessimistic Time) / 6
Putting the values into formula:
= (2 + (4 x 5) + 10)/ 6
= (2 + 20 + 10) / 6
= 5.33
To know more about PERT network visit:
brainly.com/question/17464130
#SPJ4
Answer:
I think
if angle 3=128
then angle 5=128 too because 3 and 5 are alternate interior angles
m8=180-128(linear pair)
=52°
hope it helps ❤️❤️
No parenthesis are needed, but if it made me add them I would do it like so: (12-10) + (1 * 10).