Answer:
Dr. Work in process $49,500
Dr. Material Quantity Variance $4,500
Cr. Raw material Inventory $49,500
Explanation:
First we need to calculate the Material usage variance
Standard Material = 5,500 cakes x 3 pounds = 16,500 pounds
Standard cost of Standard Material = 16,500 pounds x $3 = $49,500
Actual usage at standard cost = 16,650 pounds x $3 = $49,950
Material usage Variance = $49,950 - $49,500 = $450 unfavorable
When the actual cost incurred is more than the standard cost the variance is unfavorable.