The equivalent units of material is 2080, labor is 1560 and overhead is 1560.
What are equivalent units of materials, labor, and overhead ?
Equivalent units describe how important work has been done on a certain number of physical particulars.
To simply calculate Equivalent units, you can multiply the number of physical particulars by the chance of the work done on them. For two particulars that are 50 done, you would have one original unit ( 2 x 50 = 1).
Process going requires incompletely completed units in ending work- in- process force to be converted to the original completed units( called original units).
Equivalent units are calculated by multiplying the number of physical ( or factual) units on hand by the chance of completion of the units.
The whole unit is 2600,
and,
material = 80%, that is 2080
labor = 60%, that is 1560
overhead = 60%, that is 1560.
So, The equivalent units of material is 2080, labor is 1560 and overhead is 1560.
Learn more about equivalent units here:
brainly.com/question/14914835
#SPJ4