Answer:
A) True
Explanation:
Monumental can discharge the contract by frustration. In order for a contract to be discharged by frustration, four conditions have to occur:
- An unforeseeable event must occur: In this case the zoning changes were unforeseeable.
-
No party is at fault: the zoning board made the changes to the zoning of the land.
- Performance is impossible: there is no reason why an office building should be built in a residential only area.
- The result is radically different than expected: neither Monumental or Champion Builders expected a zoning change to occur.
To prioritize showing that ad, the type of video creative optimization to use would be dynamic creative optimization
<h3>What is Video Creative Optimization?</h3>
This refers to the use of visual effects to make a media file or video come out better by making some changes to it.
Hence, we can see that based on the fact that there are different 30-second videos and get feedback from customers, the use of dynamic creative optimization would be encouraged so that each ad would be prioritized.
Read more about video optimization here:
brainly.com/question/14276284
#SPJ1
The answer is B,"Yes, eventually their debts must be repaid with interest.
It is called value factor. There are two kinds of value factor one is present value factor and second is future value factor. The business or anything in the business has their value on their own. The future value factor is used to calculate the future value of the amount per dollar of its present value. It is the amount greater than a dollar and you can see this on the table when you calculate the future value or FV. Present Value factor is based on the time and money when you borrow or it is the debt that can grow in the span of time.
Answer:
C. subject to review by higher levels of management in order to prevent the budgets from becoming too loose.
Explanation:
Self-imposed budgets typically are subject to review by higher levels of management in order to prevent the budgets from becoming too loose.
Self-imposed budget also known as the participative budget is a type of budget where individuals having responsibility for controlling costs, prepares their own budget estimates and present them to the top level of management for review.