Answer:
By using the EOQ model, ray should order 22.8 units or 23 units each time
Explanation:
Solution
Recall that:
Ray annual estimated demand for this model is = 1,050 units
The cost of one unit carry is =$105
He estimated each order costs to place = $26
Now,
The EOQ model= (2*annual demand*ordering cost/holding cost per unit per year)^.5
Thus,
EOQ = (2*1050*26/105)^.5
EOQ = 22.8 units or 23 units