Answer:
The delivery cycle time was 26.9
Explanation:
The delivery cycle time is computed as:
Delivery cycle time = Wait time + Throughput time
where
Wait time is 13.6
The formula for computing the throughput time is as:
Throughput time = Move time + Process time + Queue time + Inspection time
where
Move time is 3.3
Process time is 2.7
Queue time is 7.0
Inspection time is 0.3
Putting values above:
Throughput time = 3.3 + 2.7 + 7.0 + 0.3
Throughput time = 13.3
Now, putting both the values above:
Delivery cycle time = 13.6 + 13.3
Delivery cycle time = 26.9
The answer to the question above is letter C. The income that is not used for consumption is called a SAVINGS. Saving consist of the amount left over when the cost of a person's consumer expenditure is subtracted from the amount of disposable income he or she earns.
Answer:
different time horizon
Explanation:
The time horizon is a certain time when a planned event/process expected to be finished. A different department can have different considerations/priorities when making the ideal time horizon. In this case, the marketing team wants the product released faster(in the first quarter) to capture market share as the main consideration. But the production team who responsible for the product quality wants more time to develop the product.
Explanation:
<em>Structure of the information systems in Health Network:</em>
-Software: It is made up of 1000 production servers that make it possible for users to access the different services through the web.
-Hardware: It is made up of the three data centers that are the sites or facilities that contain the information systems, we can also include the 650 corporate laptops and mobile devices.
-Personal: These are the users who receive the benefits, such as all the potential clients, the doctors who provide their services, and all the personnel who work in the data centers.
<em>Main objective and scope of the project in Health Network:</em>
A risk mitigation plan must be developed that allows to face the various threats previously identified.
As the main scope of the project, a BCP (business continuity plan) must be developed that allows employees to continue working remotely and safely from the web.
A computer strategy should be considered that allows employees to access the payroll and accounting application from their homes during winter storms.