I believe you meant "why is the number of shifts multiplied by approximately 4.5 to obtain the total number of operators required to run the plant"
Answer and Explanation:
There are 3 shifts per day, 49 weeks per year and 5 shifts per operator per week
To get total number of operators required to run the plant, we multiply number of shifts in a year by number if operators per shift.
49 weeks×5 shifts= 245 shifts per operator per year
365×3 shifts= 1095 shifts per year
1095/245=4.5 operators per shift
total number of operators required to run the plant(per day) = 4.5×3= 13.5 approximately 14
total number of operators required to run the plant(per year) =4.5×1095=4927.5 approximately 4928
Yes they can! Just because two plots have the same IQR and range, does not mean that the rest of the data has to be the exact same. For example, the median.
The volumes of spheres are proportional to R³. So their 'R's
are proportional to ∛their volumes.
(729/ 27) = 27
∛27 = <u>exactly 3</u> . No rounding required.
CI is congruent to AI
Step-by-step explanation:
Congruent means they are identical, CI and AI are identical
I need to find the length of something when I am given the volume, width, and height.
v=lwh
l = v/wh
Hope this helps!