The more the number of players in an industry the more it gets congested and especially for the competing sellers. The decision for increasing or reducing price is met by follower firms to do the same thing. It gets less competitive because you know all the players in the industry would be following the same practices and doing the same thing.
<span>This will lead to a flattening of the overall organization. This will allow the management to be closer to the end consumer, giving a better overall customer service reputation as well as a cost savings in not having to have as many levels of bureaucracy to go through on the part of the consumer.</span>
I think it’s C, please forgive me if I’m wrong
Answer: True
Explanation:
When a project manager is confronted with resource overload, an activity that is not on the critical path can be delayed in order not to unnecessarily delay the project. The non-critcal activities can be delayed than an amount no longer than the slack period. This levels demand for that worker.
The answer to this question is a Request for Proposal. The request for proposal or RFP is a document requested and being sent to various suppliers / sub-contractors in order to present their company's services and cost of goods or services. It is also a document that is presented thru a bidding process in order to get the project from a certain company.